● Capacity: 1x75t/h medium temperature and medium pressure boiler+1x12MW steam turbine generator set and supporting facilities
● Owner: Shunde Jinfeng Thermal Energy Co., Ltd
● Construction site: Shunde, Guangdong
● Honor: Won the First Prize for Excellent General Contracting Projects by China Investigation and Design Association of Light Industry.
● Project Overview: This project is an EPC general contracting project on the basis of engineering, procurement, construction, installation, trial run and, and delivery after 72 hours of normal operation.
The owner is located in Xingtan Town, Shunde District, Guangdong Province, and is a Hong Kong funded enterprise. As the only co-generation heat source point in the park, the owner is committed to providing electricity and steam for the park. Due to the rapid development of the Park and the continuous increase in steam consumption, in order to stabilize the steam supply demand in Xingtan Industrial Park, ensure the safety of online power supply and steam supply demand, it is necessary to build an additional 75t/h circulating fluidized bed boiler and a supporting 12MW steam turbine generator unit. The smooth operation of the project not only increases the efficiency of the company, but also greatly improves the infrastructure conditions of the Park, which is conducive to attracting investment in the Park.
With expansion, the overall layout of the factory area has not been disrupted, and conforms to the basic principles and requirements of national policies, norms, and standard, resulting in smooth process flow and pipeline, and clear functional zoning for production in the entire factory area; The transportation of goods inside and outside the factory is smooth. The layout is characterizes as having a good combination of old and new plants, easy production and management, meeting requirements of the code.